Updated Go Release Cycle (markdown)
parent
a1fecb43ee
commit
0a8c662fca
@ -28,7 +28,6 @@ to year, so milestones are specified as weeks in a particular month. Week 1 is
|
|||||||
the week starting on the first Monday of the month. All dates are subject to
|
the week starting on the first Monday of the month. All dates are subject to
|
||||||
change based on the year's holiday timings.
|
change based on the year's holiday timings.
|
||||||
|
|
||||||
|
|
||||||

|

|
||||||
|
|
||||||
#### January / July week 1: Planning for release begins.
|
#### January / July week 1: Planning for release begins.
|
||||||
@ -42,8 +41,8 @@ Example: [Go 1.20](https://groups.google.com/g/golang-dev/c/V8ez4YunkeE)
|
|||||||
|
|
||||||
Once the prior release has entered its final stabilization period, the tree
|
Once the prior release has entered its final stabilization period, the tree
|
||||||
opens for general development. All kinds of development are welcome during this
|
opens for general development. All kinds of development are welcome during this
|
||||||
period. It's preferable for large or particularly risky changes to land well before
|
period. It's preferable for large or particularly risky changes to land well
|
||||||
the end of the development window, so that there's time to fix any
|
before the end of the development window, so that there's time to fix any
|
||||||
problems that arise with them.
|
problems that arise with them.
|
||||||
|
|
||||||
#### May / November week 4: Release freeze begins.
|
#### May / November week 4: Release freeze begins.
|
||||||
@ -101,6 +100,16 @@ The calm period between a release candidate and the final release is a good time
|
|||||||
for additional testing or for discussing the next release (see the planning
|
for additional testing or for discussing the next release (see the planning
|
||||||
milestone above).
|
milestone above).
|
||||||
|
|
||||||
|
#### July / January week 3: Work on the next release begins
|
||||||
|
|
||||||
|
While the current release is being stabilized, the tree reopens for work on the
|
||||||
|
next. During this period, fixes intended for the current release need to be
|
||||||
|
[cherry-picked onto the release branch](https://go.dev/wiki/MinorReleases#making-cherry-pick-cls).
|
||||||
|
Unlike cherry-picks for minor releases, these changes don't need a backport
|
||||||
|
issue and don't need to be approved by the release team. As long as they're
|
||||||
|
permitted by the [freeze policy](#may--november-week-4-release-freeze-begins),
|
||||||
|
they can be reviewed and submitted like any other CL.
|
||||||
|
|
||||||
#### August / February week 2: Release issued.
|
#### August / February week 2: Release issued.
|
||||||
|
|
||||||
Finally, the release itself!
|
Finally, the release itself!
|
||||||
@ -144,7 +153,9 @@ See also the [MinorReleases](https://go.dev/wiki/MinorReleases) wiki page.
|
|||||||
|
|
||||||
## Freeze Exceptions
|
## Freeze Exceptions
|
||||||
|
|
||||||
Fix CLs that are in [scope of the freeze](#may--november-week-4-release-freeze-begins) do not need a freeze exception.
|
Fix CLs that are
|
||||||
|
[permitted by the freeze policy](#may--november-week-4-release-freeze-begins) do
|
||||||
|
not need a freeze exception.
|
||||||
|
|
||||||
Any exceptions to the freeze must be communicated to and explicitly approved by
|
Any exceptions to the freeze must be communicated to and explicitly approved by
|
||||||
the Go Release Team before the freeze. If you’d like to request an exception,
|
the Go Release Team before the freeze. If you’d like to request an exception,
|
||||||
@ -160,4 +171,4 @@ adopted for the Go 1.7 release in 2016. After years of difficult releases,
|
|||||||
testing and process improvements in 2022 and 2023 led to a timely 1.19 release.
|
testing and process improvements in 2022 and 2023 led to a timely 1.19 release.
|
||||||
For 1.20, the development window was expanded with a late freeze and early thaw.
|
For 1.20, the development window was expanded with a late freeze and early thaw.
|
||||||
These changes were formalized for the 1.21 release. We anticipate continuing to
|
These changes were formalized for the 1.21 release. We anticipate continuing to
|
||||||
ship on time.
|